Google is building its first Wyoming data centre, a $17 billion project powered largely by natural gas fuel cells with carbon capture, on a site it acquired from AI developer Crusoe. The price was not disclosed.

Google is building its first data centre in Wyoming, a project it values at $17 billion, and it has taken over the site from the AI infrastructure company that started it. The deal shows how hard it can be for independent developers to deliver these projects alone.

What Google announced

On 5 November 2026 Google said it would build a data centre in Laramie County, in the south-east of Wyoming, near the state capital Cheyenne. Google calls it a long-term, $17 billion investment. It named Tallgrass Energy, Black Hills Energy, American Electric Power (AEP) and Related Digital as partners.

The next day, Crusoe, a Denver-based AI data centre developer, confirmed that Google had acquired its Wyoming site. Crusoe said the sale completed its pre-development work: choosing the site, getting government approvals and planning how the campus would be powered. Neither company disclosed the price.

How it will be powered

Power is the main constraint on new AI data centres, and Google's plan leans on natural gas with carbon capture:

  • Fuel cells. Google says AEP will build a 702-megawatt fuel cell plant for the project, with fuel cells made in the US by Bloom Energy. Fuel cells turn natural gas into electricity through a chemical reaction rather than by burning it. Google calls this the largest planned development of its kind so far.
  • Carbon capture. Google says most of the carbon emissions from the fuel cells will be captured and stored underground at Tallgrass's nearby Eastern Wyoming Sequestration Hub. It says this brings its total contracted carbon capture capacity to nearly 1 gigawatt.
  • Gas generators. Google will also buy power from gas generators run by Tallgrass and Black Hills Energy, and is studying whether Tallgrass's gas turbines could be fitted with carbon capture too.

Google says the site will be air-cooled to limit water use, that it will pay for all the power it uses, and that it will cover infrastructure costs driven by its growth. These are Google's own commitments.

Why Crusoe sold

Crusoe and Tallgrass first announced the Wyoming campus in 2025, with plans to scale it eventually to 10 gigawatts, according to TechCrunch. Crusoe had tried to sign Google as a customer for the project. TechCrunch, citing earlier reporting, says Google raised concerns about cost and construction timelines under Crusoe's management and chose to take the project over instead. Bloomberg described the move as Google opting to run the project itself after Crusoe failed to lock in customers.

Crusoe frames it differently. Its chief executive, Chase Lochmiller, said the company's work had "set up the Wyoming project for construction and eventual operation", and that Crusoe has more than 6 gigawatts contracted and over 40 gigawatts in its pipeline. The two companies still work together: Crusoe is developing a separate Google data centre campus near Amarillo, Texas.

The local picture

Google says the project will support thousands of jobs and generate hundreds of millions of dollars in property taxes for Laramie County and its school district. It says it met more than 200 residents at a community meeting in Cheyenne, and that it and its partners are setting up a Community Council to deal with wider effects of data centre growth on the city. Reuters noted that the announcement comes amid growing political opposition to data centre projects in parts of the US.

Why it matters for business

For companies that rely on cloud AI services, the deal is a reminder that capacity depends on land, power and permits as much as on chips. Large cloud providers with deep pockets are increasingly willing to own and build sites directly rather than rent from independent developers. It also shows natural gas with carbon capture being used to power AI campuses where the grid cannot keep up.